After proving to be a bottleneck in the Zurich S-Bahn network, Zurich’s Stadelhofen Station is being expanded to increase capacity with a fourth track, surrounding tunnels, and a double-track upgrade in Tiefenbrunnen. As part of the planning consortium BEE+, we handled the general planning mandate from the construction and approval project phase through to execution. Section 3 encompasses the second Hirschengraben tunnel and its connecting structures, the second Zürichberg tunnel and its connecting structures, the second Riesbach tunnel and the double-track extension in the Tiefenbrunnen pre-cut.

Our services

  • Planning of the second Riesbach tunnel and its corresponding structures
  • Planning of the portal structure, aqueduct, overpass and retaining walls, double track, level crossing, and Tiefenbrunnen railway station
  • Providing BIM coordination (project as BIM model)
  • Conducting an environmental impact assessment
  • Traffic planning
  • Tendering process and detailed design development
  • Construction management and commissioning